View CfT Workspace
CfT: CT2443/2026 - Tender for the Restoration, Widening and Strengthening of Three (3) existing bridges between Rabat and Marsalforn Gozo in a resource efficient manner which considers wider environmental impacts
- Tender submission deadline in (days/hours):
- 16/17
- Name of Contracting Authority:
- Department of Contracts
- Published on behalf of:
- Ministry for Gozo
- Original CA name:
- Department of Contracts
- Title:
- CT2443/2026 - Tender for the Restoration, Widening and Strengthening of Three (3) existing bridges between Rabat and Marsalforn Gozo in a resource efficient manner which considers wider environmental impacts
- CfT CA Unique ID:
- CT2443/2026
- Evaluation Mechanism:
- Price/Cost Effectiveness
- Description:
- Tender for the Restoration, Widening and Strengthening of Three (3) existing bridges between Rabat and Marsalforn Gozo in a resource efficient manner which considers wider environmental impacts.
- Procurement Type:
- Works
- Directive:
- 2014/24/EU (Classic)
- Procedure:
- Accelerated open
- CfT Involves:
- A Public Contract
- CPV Codes:
-
45221119-Bridge renewal construction work
45221111-Road bridge construction work
45233223-Carriageway resurfacing works
71322300-Bridge-design services
- Inclusion of e-Auctions:
- No
- NUTS codes:
- MT00
- Estimated Contract Value (EUR):
- 3,150,000
- Above or Below EU Threshold:
- Below
- Time-limit for receipt of tenders or requests to participate:
- 09/12/2026 09:30
- Deadline for dispatching invitations:
- End of clarification period:
- 27/11/2026 09:30
- Deadline for Clarification Request Response:
- 02/12/2026 09:30
- Upload of documents within the clarifications:
- Yes
- Tenders Opening Date:
- 09/12/2026 10:00
- Allow suppliers to Register for Notifications:
- Yes
- Contract awarded in Lots:
- No
- EU funding:
- No
- Multiple tenders will be accepted:
- Yes
- Date of Publication/Invitation:
- 20/11/2026 15:22
- TED links for published notices:
- Date of Awarding:
- Does this Call fall under the scope of GPP?:
- Yes
- Certification check:
- Yes
- Post-Award Contract Review Step:
- No